Bathroom renovation

What a bathroom renovation actually involves in a Cypriot home

What a Cypriot bathroom quote covers as standard, what is charged on top, and the invisible work that decides whether the room still performs in year six.

8 min read

ByStavros Loizou· Editor, kitchens, bathrooms and finishes

Stavros covers the rooms that carry the most cost per square metre and the finishes that go into them. He tracks the order trades have to arrive in, which moves a Cypriot renovation bill further than any hourly rate does.

Published

A bathroom renovation in Cyprus is a waterproofing job with sanitaryware fitted on the end of it. Most of the risk sits in work you will never see again once the tiler leaves: where the waste pipes run, whether the floor falls towards the drain, and whether there is a bonded waterproof membrane behind and beneath the tiling in the shower area, which is the standard wet-area specification. The taps and the tiles are what you choose and what you look at. They are not what decides whether the room is still sound in year six, or whether the flat below finds out about it before you do.

Scope in plain terms

Three quite different jobs travel under the same name, and the first thing to settle is which one you are buying.

  • A repair or partial refresh. A failed shower valve, a cracked pan, blackened silicone, a slow waste. Tiling stays, layout stays, and the work is measured in hours or a day. This is where to start if the room is sound and simply tired.
  • A full refit within the existing layout. Everything out to the substrate, new waterproofing, new screed and falls, new tiling, fittings back in the same positions. This is the standard project and what price ranges usually describe.
  • A refit that moves the drainage. Soil pipes fall by gravity, so moving the WC, tray or waste in a flat normally means building the floor up to get the fall, which changes the threshold, then the door, then sometimes the flooring outside the room. In a house on a ground slab it can mean breaking concrete.

The building matters as much as the brief. In the 1970s to 1990s apartment blocks that make up so much of Strovolos and the Nicosia suburbs, where replumbing and rewiring dominate renovation work, the bathroom is usually small, often internal with no window, and served by galvanised supply pipe that can crumble when disturbed. There is frequently no isolating valve on the branch, so the block's riser has to be shut off to change a tap. None of that appears in a photograph of the room, and all of it appears in the price.

Those ranges are read from recorded quotes at page load rather than typed into this text, so they do not age here. They assume a full refit in the existing layout in a property with sound substrates. Our bathroom renovation pages break the figure down by district and the area pages record what changes locally.

What is included as standard

On a competently written Cypriot quote for a full refit, these sit inside the price and should not reappear later as extras.

Protection and dust control. Floors and the route to the front door covered, the doorway sealed. Tile removal is the dustiest operation in domestic renovation, and in a dry, still Cypriot flat that dust reaches every room.

Strip-out and disposal. Tiles, fittings, old screed and the enclosure, removed from the property. Ask whose skip it is, and be specific about the stairs if the block has no lift — a floor's worth of tile down four flights is a day of labour.

Plumbing first fix in the existing positions, with isolating valves fitted so the next repair does not need the whole flat shut down.

Electrical alterations, carried out and certified. Extract fan, lighting, shaver point, heated towel rail. Alterations to a dwelling's electrical installation are carried out and certified by a licensed electrician, and that certificate is what the supply authority relies on. Small works, real paperwork.

Tanking of the wet area. The bonded membrane behind and beneath the tiling in the shower zone, dressed into the floor and detailed at the corners and the door. This is the item that separates two otherwise identical quotes.

Screed and falls. The floor build-up and the gradient that takes water to the drain. On a level-access tray this is skilled setting-out, not a bag of mix.

Tiling, floor and walls, set out from a datum and cut around the fittings.

Second fix and sealing. Pan, cistern, basin, mixers, shower valve, waste, trap, screen, accessories, then silicone at every wet junction.

Clearing away and making good, including the door adjusted if the floor level changed and disturbed paint outside the room repaired.

What is almost always extra

None of these is a contractor being awkward. Each is a separate operation with its own material, its own drying time and sometimes its own trade.

  • Moving any drainage or waste position — the largest single swing available.
  • Replumbing beyond the room. If galvanised pipe fails where it is disturbed, the repair follows it into the wall or the corridor. Common in older blocks and rarely inside a fixed price.
  • A new circuit or consumer unit work. An electric shower or towel rail can need a dedicated circuit rather than a spur.
  • Re-plastering, where old sand-cement bedded tile takes the render off with it. The wall has to be flat again before anything bonds to it, and plaster has to dry before it can be sealed and tiled.
  • Forming a niche, recess or bench — blockwork, waterproofing detail and slow tiling in a small area.
  • Extract ducting to outside air. A bathroom needs air taken out of the building, not stirred around the room. Where the duct runs in a block is a real question and occasionally a committee question.
  • Natural stone, sealed before grouting and again afterwards, or large-format tile, where the substrate has to be flatter and the preparation is the cost rather than the tile.
  • Structural work. Taking down a wall to enlarge the room is not a fitter's decision. Whether it is load-bearing is an engineer's question, and ETEK maintains the register of engineers and technical professionals in Cyprus.
  • Compressed working, such as a rental turned round between bookings.

The parts people underestimate

Curing sets the programme, not labour. Plaster dries, tanking cures, screed sets, adhesive goes off before grouting. The sequence is strip-out, plumbing first fix, electrical first fix, tanking, screed and falls, tiling, plumbing second fix, electrical second fix, glazing and decorating — and a quote promising a finished bathroom faster than that allows is either skipping steps or will overrun.

One bathroom means one bathroom. Many Cypriot flats have a single full bathroom and the household still has to live there. Ask which days the WC is genuinely unavailable and whether it can stay connected through first fix.

The flat below is the real risk. Water reaches that ceiling before it reaches you. The inspection worth making is the one after tanking and before tiling — once tile goes on, the waterproofing is never visible again. Fifteen minutes on site protects the most expensive part of the job.

Ventilation is a climate problem, not a fan problem. Inland, Nicosia takes the widest temperature range on the island, so in January the concrete columns and beams behind the plaster run cold and moisture condenses there first — which is why the same corner blackens every year however often it is wiped. Around Oroklini, next to the salt lake, ambient humidity is high enough to affect damp-proofing specifications generally, and a bathroom in that air dries slowly. An extract that actually runs, ducted outside, beats any mould-resistant paint.

Coastal air reaches the fittings. In Kato Paphos and along exposed frontage the air is salt-laden, which is why galvanised and marine-grade fixings are standard there. Plating on cheap brassware and the fixings on a shower screen show it first. Order tile early, too, and keep a small surplus from the same batch — replacing a cracked tile in year four from a different batch is a visible repair.

VAT can move the total. Renovation and repair of a private residence in use more than three years can be invoiced at the reduced VAT rate of 5% rather than the standard 19%, provided the value of the materials does not exceed 50% of the value of the services. A bathroom heavy on imported sanitaryware and stone can fail that condition where a labour-heavy refit passes it comfortably. Ask which rate was quoted and on what basis, and confirm current conditions with the Tax Department.

Common questions

Can a bathroom be repaired instead of renovated?

Frequently, and it is the cheaper honest answer when the substrate is sound. A failed valve, a dropped screen, tired silicone, a slow waste and a single cracked tile are all repairs. What is not a repair is water appearing below, tiles sounding hollow across the shower wall, or a floor that has never drained properly. Those point at the waterproofing or the falls, and neither can be reached without taking the tiling off.

What counts as an emergency, and what can be done quickly?

A live leak, a blocked soil stack or no working WC in a single-bathroom home. A plumber can isolate, make safe and get the room working again quickly. A refit cannot be an emergency job, because tanking and screed keep their own timetable. When something fails suddenly, stabilise now and plan the refit afterwards rather than letting a burst pipe choose your tiles.

How long is the bathroom out of use?

For a full refit in the existing layout, think in working days spread across weeks, with curing sitting between the trades; moving drainage adds to it. Ask for the programme as a list of stages with the unusable days marked, and hold the contractor to the stages rather than to a completion date.

Does a bathroom refit need a permit?

Replacing fittings and finishes inside an existing bathroom, with no change to structure, layout or external appearance, sits outside permit scope. It changes if you take down a wall, form a new window, or alter the building's drainage arrangement. In an apartment block there is a separate, non-planning question: the management committee's rules on working hours, lift use and common pipework.

What should I keep after the job is finished?

The electrical certificate, the literature for the waterproofing system and the shower valve, invoices showing the VAT rate applied, the tile reference and batch, and photographs of the tanking and pipe runs taken before tiling. That last one costs nothing and is worth a great deal the first time anyone opens a wall.

Bathroom renovation firms in Cyprus

8 companies covering this area.

Sources

  1. Cyprus Scientific and Technical Chamber (ETEK) — technical practice — retrieved 2026-07-29
  2. Electricity Authority of Cyprus — installation and connection requirements — retrieved 2026-07-29
  3. Tax Department — VAT rates and reduced-rate conditions — retrieved 2026-07-29
  4. Department of Town Planning and Housing — scope of planning control — retrieved 2026-07-29

Thinking of doing this?Get up to five quotes, free.

Describe the project and we will gather quotes from companies that can handle the whole sequence.

Get up to 5 quotes.Free, with no obligation.

Tell us briefly what you need. We gather quotes from qualified companies where you live, so you do not have to ring round yourself.

Free · No obligation · You decide whether to go ahead